Call us now on: 01283 512 111
Next Day Delivery icon
Order in the next00:00:00for 
Next Working Day Delivery!
Login

Guaranteed Delivery within 5 working days of placing your order on selected products - See Terms and Conditions to find out more!

Timber fencing
Tameside
TCB Grounds Maintenance Ltd - Timber Acoustic Fencing
18 December, 2024

Mental Health Services Department Renovation

With New Timber Acoustic Fencing

Client: TCB Grounds Maintenance Ltd

Location: Tameside

Project:

Background & Context

  • Project Scope: TCB Grounds Maintenance was commissioned by Tameside and Glossop Integrated Care NHS Foundation Trust to provide and install an acoustic timber fence, as well as to repave the fire escape areas for the Mental Health Services department located on Fountain Street.
  • The Industry: The NHS allocates an average of £10.2 billion annually to maintain its estate, which includes essential upkeep and improvements to physical perimeter fencing. This investment supports security, safety, and noise reduction needs across NHS facilities.
  • Key Stakeholders: Funded directly by NHS Tameside, this project aimed to enhance the well-being of patients in recovery. Compliance with BS EN 1793 standards for noise-reducing devices added value for stakeholders and, most importantly, benefited the patients.

Objectives

  • Project Benchmarks: Project progress was closely monitored through specific installation milestones, including strict adherence to onsite and off-site schedules. This approach ensured minimal disruption, allowing patients in the adjacent wing to have adequate rest throughout the project.
  • Time Frame: All project work, encompassing the installation of fencing and the enhancement of fire exit routes, needed to be finalised by October 31st. The schedule allocated only one day for the assembly of the fencing, followed by three days dedicated to paving and landscaping the fire exit route to ensure timely completion.
  • Limitations: TCB Grounds Maintenance sought an acoustic fence supplier capable of delivering within two weeks of order placement. After exploring various options, they selected First Fence for its competitive lead times, offering a two-week delivery for all acoustic EchoGroove panels. In contrast, the nearest competitor had a minimum lead time of four weeks for a similar system.
  • Key Challenges: The delivery of all materials, including fencing components, posts, and post mix, had to be conducted by lifting them over the existing fencing, as all workers were locked in. This was necessary to ensure that the physical perimeter fence remained in place, prioritising the well-being of all patients.

Approach & Strategy

  • Our Approach: TCB Grounds Maintenance initially worked with Reece Beckett, a sales advisor from First Fence. "Reece was exceptionally helpful in helping us achieve our two-week lead time, which was non-negotiable for this project due to the set date for the fire exit route," explains Alex Young, owner of TCB Grounds Maintenance. First Fence prioritised ensuring that the delivery could be fulfilled within the two-week timeframe as required
  • Bespoke Requirements: Unlike most projects that have easily accessible laydown areas for plant and machinery, this site required materials to be transported from a distance on foot. Therefore, First Fence needed to assist in moving and carrying all materials for the two-man installation team.
  • Responsible Team: Alex Young, the owner of TCB Grounds Maintenance, was ultimately responsible for overseeing the specification, supply, and approval of the NHS fire escape improvement program.

Solution

  • What We Supplied: First Fence supplied their EchoGroove timber acoustic panel system in loose kit form, adhering to the following standards: 
  • BS 8417 Timber Treatment

  • BS EN 1793 Road Traffic Noise Reducing Devices

  • Complies with BS EN 1794-1 and BS EN 1794-2

  • Designed in accordance with Highways Works Clause 2504

  • Expectations: Alex Young of TCB Grounds Maintenance remarked, "We were amazed by the quality of the timber infill slats on this system; the quality was far superior to the existing acoustic fencing system on site."
  • Lessons Learned: While having more time to plan and execute this type of project would have been ideal, there were no major lessons learned, other than perhaps aiming for better site access next time

Testimonial

“I wouldn’t hesitate to use First Fence again due to their quick lead times and quality product.

Given the critical timeframes and access challenges of this project, they were the ideal supplier—10/10.”

Alex Young, TCB Grounds Maintenance Owner

College of images showing timber acoustic fencing installation
Contact our Sales Team on 01283 512 111 or at for all your fencing requirements